Production

Production stages

Stage 1. November, 2017 - February, 2018

Launch manufacturing of two SR-3 complexes

Pilot test model will be manufactured at one of the local factories within 3 months period

Stage 2. November, 2017 - June, 2018

Licensing

In process of collecting required documentation for wastes processing license

Stage 3. February, 2017 - June, 2018

Certification of machinery

Process of passing machinery certification

Stage 4. February, 2017 - June, 2018

Pilot-model industrial testing

Start of pilot-model industrial testing. Delivery and commissioning of machinery on site

Stage 5. June 2018

Pilot-model industrial testing results report.

Patent application on technology

Stage 6. February, 2017 - June, 2018

Initial preparation for industrial scale manufacturing

Plant acquirement and modernization